PeopleSoft/SQR technical development PeopleSoft/SQR technical development PeopleSoft/SQR technical development
• Mail/phone
  Search
  Keyword:
  Tools
SQR Debugger
 
 
 
TECH TALK
Lightly technical observations on PeopleSoft and related topics
 

May 17, 2006

Working Within Waterfall

Last week's post talked a little about the Waterfall model for system development. This model was introduced in 1970 by W.W. Royce, who wrote that the basic model is "risky and invites failure." This model was eagerly adopted by the IT profession. Royce proposed fixes to the model, but those were largely ignored in favor of the basic risky failure-inviter. Even now, when some of the issues addressed by the 1970 model no longer exist, people still follow it. A few of the many problems inherent in the model were listed last week. But all is not lost. There are still ways of working effectively within even a strict, basic Waterfall model.

First, as I'm sure you have noticed, there is wide variation in levels of adherence to the model. You may find yourself on a project that is scheduled using pure Waterfall principles, but notice that they are not followed in practice. They might be outlined in detail during the project kickoff meeting and then promptly forgotten. This is one extreme and it is not really a good thing.

Another variation is the calendar-driven project. The project manager says that June is the month for the Design Phase. In a pure Waterfall project, this means that all design activities—and only design activities—must occur during the month of June. But in some projects, this really means that any activity occurring during June is labelled "design." "The program I'm writing is needed to help me finish the design document."

This may be an example of a common situation—the project manager doesn't really believe in the model and is just acting under some sort of corporate mandate. He or she may be a part of the conspiracy, allowing whatever work makes sense and just stamping all of it as "design." I've been on a few of these projects. It's amusing to see how pleased everyone is when the Design Phase ends exactly on June 30—right on schedule!

Even if Waterfall is really being followed, we should not just waste time. If we need to do something necessary to advance the project, but it's not time for that activity according to the schedule, we need to let the project manager know. Most PMs will be happy to see that progress is being made. In any case, we can always do whatever preparation is necessary to be ready to start the activity. (You might even consider coding and object creation as one of those "preparation" steps.)

We can't sit on our hands and blame the schedule. If you are a consultant concerned about losing hours because you finished your task too quickly, don't worry. If the Waterfall model is really being strictly followed, there will be plenty of problems late in the project. You'll be busy! And in the meantime, you could head over to www.waterfall2006.com for a good spoof of the model.

Applications Unlimited

Bill writes to point out that Oracle's plan to continue enhancing PeopleSoft (and its other products) comes with some big disclaimers to the effect that it cannot be incorporated into a contract, it is not a commitment, and it cannot be relied on to make purchase decisions.

This appears to be standard boilerplate to protect Oracle from being locked in. Similar wording appears in various places on the Oracle site. But it's a reminder, I guess, that Applications Unlimited is Oracle's plan today. What happens in the future remains to be seen.

Until next time...







 

  HOME  |  ABOUT US  |  PRODUCTS  |  SERVICES  |  TECH TALK  |  LINKS  |  SQR  |  CONTACT
© 2003-2010 SparkPath Technologies, Inc. & its licensors. All rights reserved. Trademarks used are property of their respective owners. | Terms of Use